Bahrain
CLIENT |
DATE |
LOCATION |
DESCRIPTION |
---|---|---|---|
MCSC |
2009 |
GPIC & MCSC Shop |
NDT & PWHT on CDR Project |
Alstom Power |
2008-2009 |
Riffa Power Plant |
NDT on piping joints |
Alstom Power |
2008-2009 |
Alba |
NDT on piping joints |
Ramsis Engineering |
2008-2009 |
Ramis Shop |
Radiography Testing on PetrofacVessels |
Ahmed Mansoor Al A’ali |
2008-2009 |
AMA shop |
Radiography Testing on QatalamProject |
Ahmed Mansoor Al A’ali |
2008-2009 |
Bahrain Bay |
NDT on piping joints |
BAPCO |
2008-Ongoing |
BAPCO Refinery |
Heat Treatment Term Contract. |
BAPCO |
2007-Ongoing |
BAPCO Down stream |
NDT & Related Analysis forTerm Contract |
MCSC |
2007 |
GPIC, Manama |
NDT, ToFD, PWHT for Plant Shutdown. |
GPIC |
2007 |
GPIC, Manana |
NDT, ToFD, PWHT and Plant Inspectionfor Shutdown |
MCSC |
2007-Ongoing |
RGDP |
NDT and PWHT-Pipe Spools |
NAM |
2007-Ongoing |
RGDP |
NDT and PWHT-Pipe Spools |
Alhussam |
2007 |
Manama Financial Harbour |
NDT-Pipe Spools |
BAPCO |
2007 |
BAPCO Refinery |
NDT/PWHT Annual Shutdown |
Ahmed Mansoor Al A’ali |
2007 |
Manama Financial Harbour |
NDT-Pipe Spools and PressureVessels |
Ramsis Engineering |
2007 |
Manama Fab Shop |
NDT-Pipe Spools and PressureVessels |
Bahrain National Gas |
2007 |
BANAGAS |
NDT and Manpower Supply (QCI) forAnnual Shutdown. |
Nass, MCSC, Raffa |
2006-2007 |
BAPCO Well Heads |
NDT and PWHT Onshore Well Head Piping Spools |
Alstom Power, Mansoor, Sacn Tech,Alsa Al Husam |
2006-2007 |
Hidd Power Station |
NDT and PWHT on Hidd Phase III |
Sampyung Construction |
2005-2007 |
Al Ezzel Power Project |
NDT and PWHT. |
JGC |
2005-2007 |
BAPCO LSDP Project |
NDT and Heat Treatment works,Pressure vessels and piping. |
Doosan Heavy Industries |
2005-2007 |
Al Ezzel Power Project |
NDT and PWHT |
Ahmed Mansoor Al A’ali |
2004-2005 |
Alba-Line 5 Project |
NDT, Pre heat & PWHT |
CCIC |
2006 |
BAPCO LSDP Project |
PWHT Pipe Spools-Electric Furnace |
Ramsis Engineering |
2005 |
Manama Fabrication Shop |
NDT & PWHT on Adgas Columns |
MCSC |
2005 |
MCSC Fabrication yard |
PWHT Pressure Vessels-ElectricFurnace |
Siemens A G |
2004 |
Riffa power station |
PWHT |
Ramsis Engineering |
2004 |
Fabrication Shop |
PWHT of Storage Drum |
Ramsis Engineering |
2004 |
Manama Fabrication Shop |
NDT/PWHT-JGC Vessels |
Ramsis Engineering |
2004 |
Manama Fabrication Shop |
NDT/PWHT-Technip Vessels |
NCC |
2004 |
Alba-Line 5 Project |
NDT Pipe Spools |
CSC |
2004 |
Bapco Refinery Pipelines |
NDT Pipe Spools |
Bapco |
2004 |
BAPCO Refinery |
NDT/PWHT-Annual Shutdown |
Banagas |
2004 |
Sitra Facility |
Manpower Supply (NDT Techs) |
BANAGAS |
2004 |
Main plant shut down |
Manpower Supply Plant Inspector & Technicians |
Alstom-Swis |
2004 |
Alba-Line 5 Project |
NDT-Pipe Spools |
Panorama Contracting |
2004 |
Fabrication Shop |
PWHT on tank shell Plates |
MMETC. Co. WLL |
2004 |
Hidd Power Plant |
NDT/PWHT Pipe Spools-Hidd Phase-1 |
Austrian Energy |
2004 |
Sitra power plant |
PWHT & thermocouple Installationat Sitra powerplant |
Agas International |
2004 |
Sitra Jetty & Bapco |
NDT on fuel oil tanks and pipespools |
Shawnass M.E |
2003 |
Manama Fabrication Shop |
RT/PWHT Call Off Contract |
Ramsis Engineering |
2003 |
Manama Fabrication Shop |
NDT/PWHT-Alstom Piping & GPICCoils |
Ramsis Engineering |
2003 |
Manama Fabrication Shop |
NDT/PWHT-Chiyoda & JUPCPressure Vessels |
Ramsis Engineering |
2003 |
Manama Fabrication Shop |
NDT/PWHT-Various PressureVessels |
MCSC |
2003 |
Manama Fabrication Shop |
NDT/PWHT on piping for Hidd Projectand Banagas CS-7 Project |
Lahoud Engineering |
2003 |
Hidd Power Project |
NDT/PWHT on Boiler & PressurePiping |
GPIC |
2003 |
GPIC Plant shut down |
MFL Scanning on tank plates |
BANAGAS |
2003 |
Sitra Facility |
NDT-Sitra Facility |
Ramsis Engineering |
2002 |
Fabrication Shop |
NDT/PWHT-Call Off Contract |
Nass Industrial Services |
2002 |
Sitra |
NDT on 2” Gas Line |
MCSC |
2002 |
Fabrication Shop |
NDT/PWHT-Call Off Contract |
Magnum Industrial |
2002 |
Hidd |
PWHT Equipment Hire for ASRYProject |
Lahoud Engineering |
2002 |
Hidd Power Project |
PWHT/NDT on Boiler & PressurePiping |
Habib Ali Awachi |
2002 |
Sitra Power Plant |
PWHT at Sitra Power Plant RewampProject |
BAPCO |
2002 |
Refinery |
PWHT-Annual Shutdown |
BANAGAS |
2002 |
Sitra Facility |
MFL, NDT and Thermography-AnnualShutdown |
Raymond International |
2001 |
Hidd |
NDT on underground pipe spoolsjoints-Hidd Water Transmission Project |
Ramsis Engineering |
2001 |
Manama Fabrication Shop |
NDT/PWHT-Pressure Vessels |
MCSC |
2001 |
Refinery |
NDT in KeroMerox Project-BAPCO |
Habib Ali Awachi |
2001 |
Sitra Power Plant |
PWHT at Sitra Power Plant RewampProject |
DSD |
2001 |
Alba Jetty |
NDT/PWHT in Alba Jetty FacilityExpansion Project |
BANOCO |
2001 |
Bahrain Oil Fields |
NDT on well heads and pipelines |
BANAGAS |
2001 |
Sitra Facility |
NDT of Compressor Parts |
ASRY |
2001 |
Hidd |
PWHT on spud cans and legs of Jackup Rig |
Shawnass |
2000 |
Fabrication Shop |
NDT/PWHT Call Off Contract. |
Raymond International |
2000 |
Hidd |
NDT on underground piping jointsfor Hidd Water Transmission Project |